| Priority | Item | Tel | Class | Who | Notes |
| A | Mirror actuator air leaks | Both | HW | Mech Tech & Tel Eng | Work starting this week (6/20/04); this is a continuing project that will last a long time |
| A | Guider cameras; need spares on-site | Both | HW | SBS tech | In progress; HW shipped to OCIW for work by Estrada (6/04; Jorge is working on boards sent back from LCO |
| A | M1 coolant mixing valves | Both | HW | SBS Mech Eng, Mech tech, Tel Eng | work in progress (6/30/04); Charlie wants pressure measurements before and after the valve (11/03/04); No way to get pressures; Deadline is Mar 2005 (11/10/04); mixing valve carried by Charlie and installed in Feb; still noisy; FP will call CH |
| A | Connect shop air to instruments | Both | HW | Mech Tech & Tel Eng | In progress (6/30/04); dryer installed on compressor but more tests needed to check on humidity and ice problems (8/11/04); on hold while compressor problems being researched (4/7/05) |
| A | M2 M3 Baffles (MagIC) | Clay | HW | SBS Mech Eng, Tel Eng, Mag Mgr | Promoted 1/21/04; Charlie supplied sizes to AU; AU will review and send dimensions for M3 fitting August 2004; M3 baffle will be installed in Nov 2004, with D. Osip taking flats before and after installation (11/10/04) |
| A | IMACS commissioning | Baade | HW | Dressler et al., Inst Sci, Tel Op, Tel Eng | Jan & Feb 2005 scheduled for commissioning; Zemax modeling needed (4/7/05) |
| A | Mirror support PC boards (new SOML) | Both | HW | SBS Elec Eng, Tel Eng, Mech Tech | Promoted 1/21/04; SOML busy with LBT; not critical; Bagish will work on this (8/11/04); Prototype boards ready for fab (11/6/04) |
| A | M3 turrent geometry & telescope collimation | Both | SW | Charlie? LCO tech (Jose?) | Algorithm for driving mirror to a particular position given the motor and sensor positions; LVDTs are noisy and also not in-line with actuators so the geometry is tricky (4/7/05) |
| A | Rotator guiding | Both | HW/SW | Tel Eng, LCO Mgr, Comp | Will do as engineering time becomes available; Jose needs to tune rotator motors (4/7/05) |
| A | Solve rotator handshaking problems | Both | HW/SW | Elec tech, LCO programmer | AU will find Adam module replacement (handshaking problem) |
| A | Lightning protection on serial lines | Both | HW/SW | Elec tech | Added 4/7/05 |
| Priority | Item | Tel | Class | Who | Notes |
| B | ADC control | Baade | HW | SBS Mech Eng, Tel Eng, Comp, Mech Tech | Promoted 3/2/04; Installed and first tested 5/9/04; Lab tests on motor torque in progress (Leroy 6/30/04); on hold for IMACS; demoted to B (4/7/05) |
| B | M3 turrent on Clay | Clay | HW/SW | SBS Mech Eng, Tel Eng, Mech Tech, Elec Tech, Comp | New detent procedure with Galil amps to be tried this week (6/30/04); working but not fully testing (8/11/04); Detents will be tested in Nov 2004 engineering time but these are considered done (11/10/04); Detent problem to be fixed by Charlie (4/7/05); demoted to B (4/7/05) |
| B | Iodine cell actuator | Clay | HW/SW | Mech Tech, Tel Eng, Inst Sci | IMS modules out for repair; air-shipped October 2004; installation during Nov 2004 engineering time; Demoted to B (4/7/05) |
| B | Remote quartz halogen lamps | Both | HW | - | - |
| B | Guider mechanicals | Both | HW | Mag Mgr, SBS Mech Eng | AU will initiate guider requirements discussions; FourStar will want a new guider (8/11/04); demoted from A (11/10/04) |
| B | Flat field screens | Both | HW | - | - |
| B | Replace Glentek amps on rotators | Both | HW/SW | Mech Tech, Elec Tech, Tel Eng | Promoted 3/2/04; AU will find Adam module replacement for handshaking problem; 6/30/04; IMACS will get next setup (8/11/04); Worst problems solved, get final parts list and build the lot (11/10/04) |
| B | EDS tools | Both | SW | Mag Mgr | AU has started work on this (6/30/04) |
| B | ADC dispersion test plan | Baade | OBS | AU will think about this | - |
| B | Baffling for IMACS imaging | Baade | HW | - | - |
| B | Data PC rack & connections, equip room | Both | HW | - | - |
| B | Cass Rotator | Clay | HW | - | - |
| B | #8 dome truck | Baade | HW | - | Demoted 1/21/04 |
| B | Lift automated controls | Both | HW | - | - |
| B | Fire suppression on lift hydraulics | Both | HW | - | - |
| B | M3 Turrent | Baade | HW | - | - |
| B | ESTOP display panel | Both | HW/SW | - | - |
| B | ADC Control SW (task list from Charlie) | Baade | SW | - | - |
| B | M2 tip-tilt | Both | SW | - | - |
| B | Alarm for mirror support failures | Both | SW | - | - |
| B | Error logging & tracking | Both | SW | - | - |
| B | Lockpin interlocks everywhere | Both | SW | - | - |
| B | IMACS slitmask .nc file errors | Baade | SW | - | - |
| B | Non-sidereal & MIRAC tracking | Both | SW | - | - |
| B | Video switch control | Both | SW | - | - |
| B | Tie down video monitors in control room | Both | HW | - | - |
| C | Cryotiger recharge kit: make it work | Both | HW | - | - |
| C | AZ oil system covers | Both | HW | - | - |
| C | Dome aluminum tape | Both | HW | - | - |
| C | Fixed floor rotating seal | Both | HW | - | - |
| C | FP3 | Baade | HW | - | - |
| C | FP2 | Baade | HW | - | - |
| C | Louver seals | Both | HW | - | - |
| C | LDSSThermal | Clay | HW | - | - |
| C | M2 tip-tilt | Baade | HW | SBS | Done on Clay |
| C | Panic @ FP3 | Baade | HW | - | - |
| C | Replace lift access doors | Both | HW | - | - |
| C | Rotating dome seal | Both | HW | - | - |
| C | Separate air for instruments | Both | HW | - | - |
| C | Small ADC Mike | Clay | HW | - | - |
| C | Windscreen | Baade | HW | - | - |
| C | Upgrade TCS computers | Both | HW | - | - |
| C | TCS signal for big compressors status | Both | HW/SW | - | - |
| D | Clay bearing deflection (measure Baade) | Clay | HW | - | 12/16/2003 |
| D | E-stop interlock IMACS rotation | Baade | HW | - | 12/16/2003 |
| D | Fix/upgrade mirror covers | Both | HW | - | 12/16/2003 |
| D | HVAC controls | Both | HW | - | 12/16/2003 |
| D | TCS upgrades for interlocks | Both | HW | - | 12/26/2003 |
| D | Rotators | Both | HW | - | 01/13/2004 |
| D | Safety walk-through | Both | HW/SW | - | 12/16/2003 |
| D | TCS upgrades for interlocks | Both | SW | - | - |
| D | Elevation drive bearing inspection and repair | Clay | HW | Tel Eng, Mech Tech | Recent AZ drive failure prompts inspection and re-greasing. This will be done during the Nov 2004 engineering time |
| D | Design new mirror actuator card | Both | HW | Alan Bagish | Done |
March 18, 2005 11 AM Pacific time
Agenda
Instrument engineering detail
MIKE
LDSS3
GUIDERS
IMACS (All of this work will take place in the CCD lab in the support building. We would like the dewar to be warmed up in time to start working on it on March 24.)
|